PROCEDURE MAP  
PROCESS CONTROL – ROLLING MILLS

 

TOWERS AND STRUCTURES

This procedure is carried out for transmission towers manufacturing. The other activities attached with the process are cutting, marking, drilling/punching, bending, number stamping, temporary stacking and allied galvanizing, bundling and stacking for final dispatch. Prior to start of regular production, a sample piece is first made and thoroughly checked by the inspection to ensure dimensional and geometrical accuracy with assembly drawings.

e.  GALVANIZING

The process is done with the following steps respectively.

  i)  Pickling

This is done is dilute HCl solution to clean the surface of steel from rust/scale.

- Bath Composition:      HCl % =           20 Acid Strength

                                                                        Fe %    =          0

ii)         Rinsing

Rinsing is done in the tank of running tap water to remove the acid traces. Water is drained off from the tank after every six hours of working.  

iii)       Fluxing

To prevent the process of oxidation on steel prior to dip in the zinc bath for getting a smooth and thin coating

-Bath Composition:      Zinc Chloride              40% 100 gms/ltr of Water

Ammonium Chloride  60% 150 gms/ltr of Water

After every six months, flux bath is cleaned by decantation process.

iv)  Dipping

To attain a smooth thin film of zinc coating, steel parts are dipped in molten zinc for protecting against corrosion, steel parts dipped into zinc bath, at bath temperature of 454oC to 460o C.

  - Bath Dimensions:   Length 36 Feet, Breadth 3 Feet, Depth 3 Feet

- Bath Composition:    Zinc Purity = 99.99%

  v)  Quenching

Steel structure is quenched in tap water to relieve stresses and then is placed for quoting inspection.

vi)  Stacking

Structure after galvanizing is shifted to yard for dispatch on material flow slip. Records are maintained accordingly. 

PROCEDURE MAP CNC SHOP

TUBULAR POLES

The process applies for the production of Tubular Poles and Octagonal Poles. The following procedure is adopted.

  i)  Squeezing of Pipe

One end of the base pipe is reduced on squeezing machine so as to get it fit-in with outer dia of the upper pipe.

ii) Bending of Pipe

Upper pipe is bended on the bending machine that is known as Arm Pipe. Its bending is done according to the radius and design of the tubular pole. 

iii) Jig Formation

Welding jigs are made according to the total height of the tubular pole.

iv)  Stand of Rolls

It is made so that the pipe used for the formation of tubular poles can be rotated for welding operation.

v)  Welding

The pipe of pole is rotated with the help of the stand of rolls and joints are Electric Arc Welded with each other on outer periphery. 

vi)  Straightening

  It is done with the help of hydraulic presses.

vii)  Galvanizing

After completion, poles are shifted to Galvanizing Plant for zinc coating.

g. OCTAGONAL POLES

To manufacture octagonal poles, following procedure is adopted.

i)  Plate Cutting

Cutting of plate is done with auto gas cutting machine ensuring no burs on the cutting edges.

ii) Bending

Half octagonal shapes of plates is made on Bending Machine as per required dimensions on drawings.

iii)  Segments  

Octagonal Pole is manufactured in two/three segments, which depends on overall length of the pole.

iv)  Welding

Both half sections of octagonal shape of two/three segments are welded along the length for making complete octagonal shape. Segments are joined with each other by Electric Auto Arc welding process.

v)  Grinding

Welded joints are grinded off for smooth finish.

vi) Jig Formation

These poles are fitted with each other by hydraulic press. The segments of pole are then separated from each other for galvanizing.

vii) Galvanizing

This process is carried out on finished octagonal poles.

8.  AVAILABILITY OF INFRASTRUCTURE

Sound infrastructure is available at Mill Site and this does not pose any current or future threat. The approach to Mill Site is inhibited by wide roads making access easy. Further, electrical and gas connections have been provided at mill site which are in accordance with  projects requirement. The project has its own tube well and turbine system to look after the water needs. A compact sewerage system has been  also laid down at the project. Further, provision for full backup auxiliary power has also been provided. 

Due to abundance of steel factories in the area, labour, skilled, semi-skilled and unskilled,  is available
in abundance.